Installation Steps for Willow Creek Paving Stones
Step 2 Compacted Aggregate Base
Place and compact uniform layers of aggregate base material throughout
the excavated area until the required depth and slope is achieved. Best
results will be achieved by using a vibrating plate compactor.
,
,
Slightly moisten dry base material and compact in layers of no more than
4 inches at a time. Start at the perimeter and work your way toward the
center, overlapping each previous pass. Make at least two complete
passes to create a flat, smooth base.
Step 3 Setting Screed Guides
Paving stones are laid on a 1-inch layer of bedding sand. Screed guides
(see tool list) are used to level the bedding sand. Set screed guides
parallel to each other on the compacted aggregate base and check grade.
The top of the screed guides will be the top of your sand bed and will
determine the pitch and flatness of your paving-stone surface.
Step 4 Installing Edge Restraints
To prevent lateral movement of the paving stones and to ensure proper
interlocking, edge restraints should be installed on top of the
crushed-stone base on all unrestrained edges of your project area.
Install edging initially on only one or two sides of the project area.
This is where paver placement will begin. If possible, begin at a long,
straight edge. After all paving stones have been laid, install the
remainder of edging. Ribs of edge restraints may be easily cut to permit
bending of the restraints for curved edges. Stake edge restraints at all
ends, leaving no more than 18 inches between spikes. Note:
Circlestone comprises concentric rings of paving stones placed around
one center paving stone. After all Circlestones are installed,
place edge restraints around the perimeter of the project area.
|