Installation Steps for VERSA-LOK Standard, Cobble and Accent
Step 6 Complete Remaining Courses
Continue building your wall according to your design until all the units
are in place. You can stack up to three courses before backfilling.
Place and compact drainage aggregate up to 12 inches below the top of
the wall. Backfill the remainder with soil.
Step 7 Place and Glue Cap Units
When the desired wall height is achieved, finish the wall by placing cap
units along the top. Lay out all your cap units before securing them
with adhesive. The front of the caps may be placed flush with the front
of the wall, set back, or slightly hung over the wall face. Overhanging
the cap units about three-quarter inch will create an attractive eyebrow
on top and help hide minor imperfections in the wall’s alignment.
Secure the caps to the wall with two continuous 1/4-inch beads of
VERSA-LOK Concrete Adhesive along the top course of wall units. Your
wall may shift or move slightly—especially in areas subject to
freeze/thaw cycles. Versa-Lok Concrete Adhesive is specially formulated
to remain flexible under these conditions.
Backfill the caps with topsoil after they’re secured, complete your
final grading and landscaping and your Versa-Lok wall is complete.
,
|