Installation Steps for Handy-Stone and Handy-Wall
Step 3 Lay Succeeding Course
Position the next course of units so that the alignment lips overhand
the back edge of the base course and each unit is resting on two
adjacent lower units.
Step 4 Backfill As You Proceed
Place backfill behind each course as you proceed. Gravel backfill is
recommended to help with drainage. Any material placed behind the wall
should be well compacted. Continue laying additional courses and
backfilling until desired height is achieved (maximum wall height is 3
feet).
Step 5 Secure Top Course (Optional)
If it is critical to prevent units from being removed, secure the
uppermost course with a flexible concrete adhesive, following the
manufacturer's directions.
|