Installation Steps for Handy-Stone and Handy-Wall
Step 1 Prepare Base
Begin by excavating a trench:
15'' wide by 4'' deep for Handy-Wall
12" wide by 6'' deep for Handy-Stone
12'' wide by 4'' deep for Handy-Stone II & III.
Be sure to remove sod and other organic materials from the base.
Partially embed a portion of the lowermost units to hold them in place.
After excavating, make sure that the bottom of the trench is well
compacted. Use a hand tamper to compact the soil, if necessary. Spread a
1'' layer of sand in the trench. The base is now ready for the base
layer (or "course") of wall units.
Step 2 Position Base Course
Lay the base course units on your prepared base. You may remove a small
amount of sand to make room for the alignment lips or remove the
alignment lips using a hammer and chisel. Level each unit side to side,
front to back, and with adjacent units. A rubber mallet will help you
level the units, and a stringline can be used to keep them in a
straight line. Place the units directly next to one another, keeping
face joints tight. Place and compact soil backfill to a height that is
even with the soil in front of the wall, to hold the units securely in
place. |